Three metro lines reach the western side of Andheri West, and they are at three different stages. Line 1 has run from Versova since 2014 and is the busiest of the three. Line 2A reached Oshiwara and Andheri West in January 2023 and, in its first full year, carried under a third of what its planners forecast for 2021. Line 6, which is to start at Lokhandwala, has no opening date. It was due in 2021.
In 30 seconds
- Line 1 opened at Versova
- 2014
- Line 2A riders a day, April 2023 to March 2024
- 1.2 lakh
- Line 6's original target; no date is set
- 2021
- Sea link's expected completion, October 2026
- Dec 2028
- Line 1 has served Versova, D N Nagar and Azad Nagar since June 2014 and is the busiest of the three lines.
- Line 2A reached Oshiwara, Lower Oshiwara and Andheri West in January 2023; in its first full year it carried under a third of its 2015 forecast for 2021.
- Line 6 is to start at Swami Samarth Nagar in Lokhandwala. On 29 September the Supreme Court declined to interfere with the land order for its depot.
- A 2026 study measured Line 1's effect on the government's assessed values, not on sale prices.
- Walk to the station before you pay for a metro address.
Reported by Property Butler Research, 18 November 2026.
Line 1: the busiest of the three
Line 1 opened on 8 June 2014 and runs 12 stations from Versova to Ghatkopar, through D N Nagar, Azad Nagar and Andheri, by MMRDA's project page, which lists it as a public-private partnership run by Mumbai Metro One. In its eleventh-anniversary release in June 2025 the operator reported a weekday average of about five lakh riders, a record day of 5.47 lakh and 444 trips a day; a year later it reported a record day of 5.79 lakh and more than 125 crore commuters since 2014. MMRDA's page estimated 6.65 lakh riders a day for 2021 and gives the average day as about three lakh. It lists D N Nagar as Line 1's interchange with Line 2A.
Line 2A: open, and below its forecasts
Line 2A runs 17 elevated stations from Dahisar East to Andheri West. Its northern nine stations opened in April 2022. The stretch through Goregaon West, Oshiwara and Lower Oshiwara to Andheri West received its safety certificate on 12 January 2023 and was opened by the Prime Minister on 19 January.
In the year to March 2024, its first full year end to end, Line 2A carried an average of 35.9 lakh passengers a month, about 1.2 lakh a day, by an RTI reply reported by the Free Press Journal. Its 2015 project report, written by the Delhi Metro Rail Corporation for MMRDA, forecast 2.70 lakh trips a day for 2016 and 4.08 lakh for 2021 if the line ran on its own, and more if it was joined to the line to Mandale. Lines 2A and 7 together reached about 2.05 lakh riders a day by mid-June 2025, a quarter of the projected figure, Scroll reported.
By the numbers
Line 2A: riders a day, forecast and actual
- 2015 forecast for 2021, the line on its own4.08 lakh
- 2015 forecast for 2016, the line on its own2.70 lakh
- Average, April 2023 to March 2024about 1.2 lakh
Line 6: a start at Lokhandwala, and no date
Line 6 is to run 13 elevated stations, mostly along the median of the Jogeshwari-Vikhroli Link Road, from Swami Samarth Nagar in Lokhandwala to Vikhroli on the Eastern Express Highway. MMRDA plans interchanges with Line 2A at Adarsh Nagar and Line 7 at JVLR, and puts the project's completion cost at ₹6,716 crore. By its own figures to 31 August 2026, 97.88% of the piers and 87.35% of the station works were complete. No stretch is open.
The route
Line 6, west to east
- Swami Samarth NagarLokhandwala
The line's western end.
- Adarsh Nagar
Planned interchange with Line 2A.
- Jogeshwari (West)
- JVLR Junction
Planned interchange with Line 7.
- Shyam Nagar
- Mahakali Caves
- SEEPZ Village
- Saki Vihar Road
- Rambaug (Powai)
- Powai Lake
- IIT Powai
- Kanjurmarg (West)
The planned car depot is on salt-pan land at Kanjurmarg.
- Vikhroli EEH
Eastern end, on the Eastern Express Highway. A temporary maintenance facility is planned at Vikhroli.
Its dates have moved for years. The original target was 2021. In December 2022 an MMRDA official expected it ready by late 2024. Tenders for its trains and fire safety were cancelled in October 2023, and in July 2025 a contract of ₹2,269 crore for the trains, signalling and platform screen doors went to NCC. In January 2026 MMRDA officials spoke of opening in the second half of 2026. In April the trade journal Projects Monitor reported 87.7% of construction complete and wrote that the line was "racing towards a partial opening in early 2027". The Free Press Journal's report of 1 September 2026 gave no opening date at all.
Timeline
Line 6's dates
Original
Target: 2021.
Dec 2022
An MMRDA official expects the line ready by late 2024.
Oct 2023
Tenders for the trains and fire safety are cancelled.
Jul 2025
NCC wins the ₹2,269 crore contract for trains, signalling and platform screen doors.
Sep 2025
Pillars already built are demolished after the depot's move to an adjacent plot. No new date.
Jan 2026
MMRDA officials plan to open in the second half of 2026, without the Kanjurmarg depot.
Feb 2026
The Bombay High Court allows MMRDA to take 15 hectares of salt-pan land at Kanjurmarg.
Apr 2026
Projects Monitor reports 87.7% of construction complete and writes of a partial opening in early 2027.
Aug 2026
MMRDA reports 87.35% of the station works complete.
Sep 2026
No opening date in the Free Press Journal's report of 1 September; a temporary maintenance facility is planned at Vikhroli.
29 Sep 2026
The Supreme Court declines to interfere with the land order.
MilestoneTroubleGood news
The blocker has been the depot's land. The car depot is planned on salt-pan land at Kanjurmarg. After it was moved to an adjacent plot, some pillars already built had to be demolished, the Free Press Journal reported in September 2025. On 13 February 2026 the Bombay High Court allowed MMRDA to take 15 hectares there, and on 29 September the Supreme Court declined to interfere, mid-day reported. Meanwhile MMRDA plans a temporary elevated maintenance facility at Vikhroli, so the line can open without the depot, which would take two to three years to build once the land is handed over, the Free Press Journal reported in January.
The coastal roads
Two road projects are planned along Andheri West's coast. The Versova-Bandra Sea Link will miss its May 2028 deadline, with completion now expected in December 2028 and civil work at 35% against a target of 40%, the Indian Express reported on 25 October 2026; ThePrint had reported in July 2024 that its cost had risen from ₹7,502 crore to ₹18,121 crore. The same Indian Express report gives December 2028 for the BMC's coastal road from Versova to Bhayandar.
What a station does to prices
A study has measured what a Mumbai metro line did to property values. Palak Suri of West Virginia University and Maureen Cropper of the University of Maryland compared areas within a kilometre of Line 1 with areas 1 to 3 km away, using the government's assessed values, known as ready reckoner rates, from 2011 to 2018, and found an increase of 6 to 8 percent for residential and commercial property after the line opened (Regional Science and Urban Economics, 2026). Ready reckoner rates are official values used to calculate taxes, not the prices buyers paid, and the study covers Line 1 only. Ask any developer who quotes a metro premium for Line 2A or Line 6 where the figure comes from.
Our own asking rates in the station areas are below. They are medians of the homes we have for sale and do not separate the metro from everything else a home is priced on.
By the numbers
Median asking price per sq ft of carpet, 18 November 2026
- Versova, on Line 1 (29 homes)₹47,017
- Lokhandwala, Line 6 planned (11 homes)₹46,925
- Andheri West, all (152 homes)₹41,784
- Oshiwara, on Line 2A (13 homes)₹39,829
Our view
Line 1 is the established line, and Versova, D N Nagar and Azad Nagar have had it for twelve years. Line 2A runs, and the figures published so far put it well below its forecasts. Line 6 is planned to reach Lokhandwala, but no opening date had been announced as of September, and the court ruling on its depot land came only on 29 September. Buy a home here for what the neighbourhood offers now, and count Line 6 as a future benefit rather than a reason to pay more today.
Before you buy
If the metro is why you are buying
- Walk from the building's gate to the station you would use, at the hour you would travel.
- When a developer says a home is minutes from the metro, ask which station, and whether that line is open.
- Treat Line 6 as a future line: no opening date had been announced as of September 2026.
- Ask a developer who quotes a metro premium where the figure comes from.
- Check whether the station has a lift or an escalator going your way, if you need one.
- For the sea link and the coastal road, check the latest official date before you count on them.
Sources
- MMRDA, Metro Line 1 project page (read 18 November 2026). mmrda.maharashtra.gov.in
- MMRDA, Metro Line 2A project page (read 18 November 2026). mmrda.maharashtra.gov.in
- MMRDA, Metro Line 6 project page, status as on 31 August 2026 (read 18 November 2026). mmrda.maharashtra.gov.in
- Delhi Metro Rail Corporation for MMRDA, Detailed Project Report (Updated), Dahisar (E) to D.N. Nagar corridor, September 2015. mmrda.maharashtra.gov.in
- Free Press Journal, Mumbai Metro One marks 11 years, 7 June 2025. www.freepressjournal.in
- Free Press Journal, Metro Line 1 completes 12 years, 7 June 2026. www.freepressjournal.in
- Free Press Journal, Metro 2A and 7 receive safety certificate, 12 January 2023. www.freepressjournal.in
- Metro Rail Today, MMRDA opens phase 2 of Metro Lines 2A and 7 for the public, January 2023. metrorailtoday.com
- Free Press Journal, Metro 2A ridership: RTI reply on monthly ridership, 12 August 2024. www.freepressjournal.in
- Scroll, Urban immobility: why the Mumbai metro is failing to take off, 1 August 2025. scroll.in
- Free Press Journal, Still 2 years for Metro Line 6, 22 December 2022. www.freepressjournal.in
- Free Press Journal, Metro 6 connecting Lokhandwala to Vikhroli, 10 August 2025. www.freepressjournal.in
- Free Press Journal, Metro 6 faces fresh setback as pillars demolished following depot shift, 30 September 2025. www.freepressjournal.in
- Free Press Journal (from the Hindustan Times), MMRDA to open Pink Line without Kanjurmarg depot, 21 January 2026. www.freepressjournal.in
- Projects Monitor, 87.7% civil work of Line 6 complete, 27 April 2026. www.projectsmonitor.com
- Free Press Journal, Metro Line 6 may begin services without full depot, 1 September 2026. www.freepressjournal.in
- mid-day, Metro Line 6 gets major boost as Supreme Court declines to intervene in car shed land order, 30 September 2026. www.mid-day.com
- Indian Express, Versova-Bandra Sea Link deadline delayed to December 2028, 25 October 2026. indianexpress.com
- ThePrint, Technical changes, delays push cost of Bandra-Versova Sea Link up by over 140% in 7 years, 26 July 2024. theprint.in
- Palak Suri and Maureen L. Cropper, What are the benefits of metro rail in Mumbai, India?, Regional Science and Urban Economics, vol. 121, September 2026. www.sciencedirect.com
- Property Butler listings, 18 November 2026: the Versova, Lokhandwala, Oshiwara and Andheri West rates pages.
Corrections are made in this article with the date. Write to info@propertybutler.in.